You can pass project-specific settings to other projects. To do this, you must save the source project settings, together with the project, as a template and then create the new project from the template.
Save the project as a template
Preconditions:
- You have opened the project management: Project > Management
- In the tree structure of project management, there is an imported directory with at least one project.
- Select your source project in the Project management dialog.
- Select [Extras] > Create project template.
- Select the storage location and the name of the project template.
- Click [Save].
A project template is created.
Create projects from templates
- Select the menu item Project > New.
- Assign a name to the new project in the Create project dialog.
- Click [...] next to the Template field.
- Select the desired template in the Select project template / basic project dialog and click [Open].
- Select a storage location for the project.
- Click [OK].
A project is created on the basis of the project template.
See also