This functionality is only available for certain module packages. Info / Copyright

P004082: Configuration project '<x>' does not contain a CPU

Cause

The information that a PLC box is a CPU is missing at the PLC box. This information is required for a correct PLC data export from EPLAN.

This check run only checks PLC boxes which are main functions and at which a configuration project is entered.

Solution

  1. Locate the PLC box in the schematic using the Go to (graphic) functionality that is provided by the popup menu of the Message management dialog.
  2. Open the property dialog of the PLC box.
  3. Bring the PLC structure data tab to the front.
  4. Activate the CPU check box in the properties list.
  5. Ensure that a configuration project and a station ID are entered at the PLC box.
  6. Click [OK].
  7. Then start a new check run.

Note:

Take into account that a CPU does not have to exist at every workstation. It is sufficient if at least one CPU exists under all workstations that are assigned to a configuration project.