It is possible to use project management to automate actions for multiple projects.
Preconditions:
- You have imported directories and projects into the Project management dialog.
- You have created a scheme that contains a sequence of automatable actions.
- Project > Management
- To select several projects, hold down the [Ctrl] key and select the desired projects in the project management tree.
- Select the Automated processing popup menu item.
- In the Run: Automated processing dialog in the Scheme field, select the scheme with the automatable actions.
The sequence of actions stored in the scheme is displayed in the Actions list. - Click [OK].
The projects are automatically processed, one after the other.
See also