Projects can be backed up from the Backstage view and from the project management.
Back up projects from the Backstage view
Precondition:
You have selected a project in the page navigator.
- Select the following commands: File > Back up.
- In the Back up projects dialog, define the settings for the backup.
- Click [OK].
The project is backed up to the specified directory according to the entries you have made.
Note:
EPLAN notes these settings for each project and offers them again during later backups.
Back up projects from the project management
Preconditions:
- You have set up the project management.
- In the tree structure of project management there is an imported directory with at least one project.
- Select the following commands: File > Project management.
- Select the desired projects from the tree structure in the Project management dialog.
- Select the Back up popup menu item.
- In the Back up projects dialog, define the settings for the backup.
- Confirm your entries.
The projects are compressed one after another, and backed up to the specified directory.
See also