This functionality is only available for certain module packages. Info / Copyright

P028034: The segment has no assigned main function

Cause

With this check run you can determine whether placed functions exist in the detailed planning (in the P&I diagram or in the schematic) for segments (PCT loops or planning objects) created in the pre-planning navigator. In the concrete case there is no main function in the detailed planning for the segment existing in the pre-planning.

Solution

Possibility 1

  1. Locate the corresponding segment in the pre-planning navigator using the Synchronize selection function offered by the popup menu in the Message management dialog.

    The respective segment is marked in the pre-planning navigator.
  2. Place the segment on a page of the type "P&I diagram" or on a schematic page.

Possibility 2

Exclude the segments that do not have to be placed from the check. Define corresponding filters to this purpose.