You can import projects that were previously exported in XML format with the epj file suffix.
Backstage view: File > Import > Command group Project data > Project data > Command group Project > Project .
Project management: [Organize] > Import.
- Select the desired project in the Import project dialog.
- Click [Open].
- Check that you have selected the correct project file in the XML file field of the XML project dialog and, if necessary, click [...] to open a different project for the import.
- Select the Synchronize parts check box if automatic parts synchronization should be performed during the import.
- If necessary, enter another name in the Target project field for the project to be imported.
- Click [OK].
The project is imported and a progress bar shows the progress. If you have selected the Synchronize parts check box then, after the import, a progress bar shows the progress of the synchronization.