PartsFromSystemToProject(Project) Method
In This Topic
Synchronizes the parts stored in the project with the parts in the parts master database. Updates parts inside project. Parts in the database are not changed. This method corresponds with the EPLAN functionality in the ribbon "Master data \> Parts \> Synchronize"
Syntax
public void PartsFromSystemToProject(
Project
)
public:
void PartsFromSystemToProject(
Project^
)
Parameters
- pProject
- Project for which the parts will be updated.
Exceptions
Exception | Description |
ArgumentNullException | Thrown if null was
passed as an
argument. |
ArgumentException | Thrown in case of
invalid arguments,
e.g. the project is
not valid. |
BaseException | The synchronization
finished with
errors. |
See Also